• 2017 BOND PROJECTS
     - Ray Reynolds Middle School


    middle school #4


     

Reynolds Middle School Construction Update: May 2020 (video)


Reynolds Middle School Construction Update: March 2020 (video)


Reynolds Middle School Construction Update: Jan. 2020 (video)


Reynolds Middle School Construction Update: Nov. 2019 (video)


Reynolds Middle School Construction Update: 10/17/19

  • These aerial photos show the progress underway at Reynolds Middle School. The ironwork is complete on the two-story classroom wing to the west and crews are now working to close the building envelope. Construction continues on the gymasiums that are part of the wing to the east. Roofing has started over the locker room areas adjacent to the gyms. The bus loop that surrounds the school, and the parking lot to the north of the classroom wing are being prepped and will be paved soon.

    Reynolds Middle School construction  Reynolds Middle School construction  Reynolds Middle School construction  Reynolds Middle School construction  Reynolds Middle School construction  Reynolds Middle School construction


Reynolds Middle School Construction Update: August 2019 (video)


Reynolds Middle School Construction Update: 7/29/19

  • These aerial photos show the progress underway on Reynolds Middle School. The giant blue crane in the center is being used to "fly" the steel beams into position as crews construct the two-story classroom wing. You can also begin to see the walkways where students will walk between the classroom wing and the commons area. Crews are also making good progress building up the walls that will enclose the gymasium wing.

    Photo of Reynolds Middle School construction  Photo of Reynolds Middle School construction  Photo of Reynolds Middle School construction  Photo of Reynolds Middle School construction  Photo of Reynolds Middle School construction


Reynolds Middle School Construction Update: 6/5/19

  • These are some aerial photos taken recently at Reynolds Middle School. Fowler Construction crews have been installing underground utilities and pouring footings for the school's foundation. They have also poured the concrete slab for the gymasium floor.

    Aerial view of Reynolds Middle School construction  aerial view of Reynolds Middle School construction  aerial view of Reynolds Middle School construction


Reynolds Middle School Construction Update - May 2019 (video)


Reynolds Middle School Construction Team

  • Reynolds Middle School Construction Team

    A big "thank you" to our Reynolds Middle School construction team, including primary contractor Fowler Construction and Architect/Design Team MMEC Architecture.


Reynolds Middle School Sitework Update - Feb. 2019 (video)

Reynolds Middle School Project Timeline

  • Project Timeline Key
    Complete  Complete

    In Process  In Process

    Not yet started  Not Yet Started


    Complete  Architect selected for design work (MMEC Architectural)
    - December 2017 -

    Complete  Preliminary design work underway
    - January 2018 -

    Complete  School Board approves educational specifications
    - April 2018 -

    Complete  School Board approves schematic designs
    - June 2018 -

    Complete  Design plans reviewed
    - January-February 2019 -

    Complete  Site Work Begins
    - January 2019 -

    Complete  Construction bids for project accepted
    - March-April 2019 -

    Complete  School Board awards contract to Fowler Construction
    - April 2019 -

    In Process  Construction work begins
    - April 2019 -

    Complete  Groundbreaking Ceremony
    - May 2019 -

    Not yet started  Construction work completed
    - Late July 2020 -

    Not yet started  School open for students
    - Late August 2020 -

    Last modified: May 25, 2019


    In-Depth Design/Construction Timeline for Middle School #4

Reynolds Middle School Fact Sheet

  • Reynolds Middle School Estimated Costs:
    $46.5 million
    Local Bond: $30.6 million
    State Match: $15.9 million


    • Reynolds Middle School will be built on a parcel of land the District owns along Burns Road, between Road 90 and Broadmoor Boulevard. 

    • Reynolds Middle School will be 115,000 square feet and serve approximately 1,100 students.

     


  • ADDITIONAL PROJECTS
    (click the title below to learn more about each project)

    Three Rivers Elementary
    Columbia River Elementary
    (link) Replace and expand Stevens Middle School.
    (link) Safety and Health Improvements: School Sites.
    Transportation and Maintenance Facilities

  •  