  • Safety & Security Improvements Timeline 

    Project Timeline Key
    Complete  Complete

    In Process  In Process

    Not yet started  Not Yet Started


    Complete  Architect selected for design work of front entrance improvements (CKJT Architects)
    - April 2018 -

    Complete  Design plans completed for work at Emerson Elementary, Frost Elementary, Whittier Elementary
    - May 2018 -

    Complete  Contractor selected for work at Emerson Elementary, Frost Elementary, Whittier Elementary (Siefken & Sons Construction)
    - May 2018 -

    Complete  Construction work begins at Emerson Elementary, Frost Elementary, Whittier Elementary
    - June 2018 -

    Complete  Construction work completed at Emerson Elementary, Frost Elementary, Whittier Elementary
    - August 2018 -

    Complete  Architects visit remaining school sites
    - May 2018 -

    Complete  Design work completed for front entrance improvements at Chiawana HS, McLoughlin MS, Ochoa MS, Angelou Elementary, Chess Elementary, Robinson Elementary
    - April 2019 -

    Complete  Construction work begins for front entrance improvements at Chiawana HS, McLoughlin MS, Ochoa MS, Angelou Elementary, Chess Elementary, Robinson Elementary
    - June 2019 -

    Complete  Design work completed for front entrance improvements at Captain Gray STEM Elementary, Livingston Elementary, Markham Elementary, McGee Elementary
    - July 2019 -

    Complete  Construction work completed at Chiawana HS, McLoughlin MS, Ochoa MS, Angelou Elementary, Chess Elementary, Robinson Elementary
    - October 2019 -

    Not yet started  Construction work begins for front entrance improvements at Captain Gray STEM Elementary, Livingston Elementary, Markham Elementary, McGee Elementary
    - June 2020 -

    Not yet started  Construction work completed at Captain Gray STEM Elementary, Livingston Elementary, Markham Elementary, McGee Elementary
    - August 2020 -

     

    Last modified: November 1, 2019

     

     

  • Safety Improvements Estimated Cost:
    $900,000

    Roofing Projects Estimated Cost:
    $800,000

     • School safety and security improvements at Angelou, Captain Gray STEM, Chess, Emerson, Frost, Livingston, Longfellow, Markham, McGee, Robinson, Twain and Whittier elementary schools

    • School safety and security improvements at Ochoa and McLoughlin middle schools, and Chiawana High School

    • Roof replacements at Captain Gray STEM Elementary and Markham Elementary

     

     


  • ADDITIONAL PROJECTS
    (click the title below to learn more about each project)

    Three Rivers Elementary
    Columbia River Elementary
    (link) Replace and expand Stevens Middle School.  reynolds middle school