    Stevens MS Project Timeline


    Project Timeline Key
    Complete  Complete

    In Process  In Process

    Not yet started  Not Yet Started


     

     Complete Architect selected for design work (MMEC Architectural)
    - December 2017 -

    Complete Preliminary design work underway
    - January 2018 -

    Complete School Board approves educational specifications
    - April 2018 -

    Complete Design Plans reviewed
    - April-May 2019 -

    Complete Construction bids for project accepted
    - July 2019 -

    In Process Constuction work begins
    - August 2019 -

    Not yet started  Constuction work completed
    - December 2020 -

    Not yet started  School open for students
    - January 2021 -

    Estimated Cost:

    $39.7 million

    Local Bond: $21.1 million

    State Match: $18.6 million